Posted: 3/14/2013 9:38 AM
The Horsham Water & Sewer Authority’s sewer televising, joint testing, and grouting project is continuing into 2013. The flushing and televising portion of the project is nearly complete as of the end of 2012. Sewer Specialty Services Co., Inc. of Leicester, New York is now moving on to the joint testing and grout sealing phase of the project which will continue through May 2013. The work is concentrated primarily in the eastern portion of the Township.
On the north side of Horsham Road, this includes all areas east of Easton Road (Route 611) and Maple Avenue. South of Horsham Road, the work area extends between Norristown Road and Blair Mill Road. Working hours are Monday through Thursday beginning at approximately 7 AM through no later than 7 PM.
The joint testing and grouting phase of the project will proceed through approximately eleven “quadrants” of the Township, similar to the sequence in which the televising was conducted. The amount of time spent in each quadrant is dependent on the quadrant size, the length of the sewer within the quadrant, and the amount of required joint repair work. As a frame of reference, under normal conditions, approximately 600 – 800 LF of sewer can be tested in a single work day.
Testing is typically followed by a separate crew which will perform the necessary grout sealing work. To the extent possible, testing and grouting will be completed in each quadrant before moving to the next quadrant with the following exceptions; 1) Some areas of the sewer system are in easements and weather conditions can impact accessibility to these areas 2) many of the larger diameter interceptor sewers traverse multiple quadrants and specialized equipment is required as part of the operation, therefore, interceptor sewers will be worked in sections, by the full run of the sewer 3) sewers located in major roadways where traffic control is required may also be conducted outside of the respective quadrant.
To view the map of quadrants, please visit: www.horshamwater-sewer.org
Testing and grouting work will resume in the first quadrant, A1, on Monday, January 7, 2013 and is expected to continue in this quadrant through January 21, 2013. This quadrant includes the following streets. Unless otherwise noted, the entire street is included:
Apple Hill
Beatrice
Bender
Blair Mill – 112-118
Catbrier
Clayton
Crab Apple
Crestview
Gerstley
Meetinghouse – from Moreland to County Line Road
Mimosa
Monument
Moonflower
Oak Hill
Parkway
Quince
Sourwood
Southview
St. David’s
W. Moreland – from Blair Mill to Meetinghouse
Televising, testing and grouting work will continue on the following roads, beginning Monday, January 28, 2013 and is expected to continue through the month of February, 2013.
Apple Hill
Applewood Court
Avenue “A”
Avenue “B”
Bender Road
Blackwatch Court
Country Road
Cricket Circle
Edgewood Avenue
Heather Lane
Meadowlark Lane
Pheasant Run
Televising, testing and grouting work will continue on the following roads, beginning Monday, March 4, 2013 and is expected to continue through the month of March, 2013.
Beatrice Avenue
Clayton Road
Crestview Road
Horsham Road - 100 block
Meetinghouse Road
Moreland Avenue
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-1 Streets
Arundel Avenue
Birch Avenue
Cedar Avenue
Central Avenue
Cottage Avenue from Cedar - Summer
Edgely Avenue
Garden Avenue from Cedar - Summer
Hillside Avenue
Laurel Avenue
Milton Avenue
Oakdale Avenue
Olive Avenue
Pearl Avenue
Poplar Avenue
Summer Avenue
Upland Avenue
Westmont Avenue
Woodlawn Avenue
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-2 Streets
Arbutus Avenue – Maple to Saw Mill
Avenue “A”
Avenue “B”
Avenue “C”
Avenue “D”
Avenue “E”
Broadway Avenue – Wayne to Easton
Columbia Avenue – Watson to Easton
Edgewood Avenue
Girard Avenue – Watson to Easton
Homestead Avenue – Washington to Norristown
Horsham Road – Maple to Avenue E
Jack Ladder Lane
Jefferson Avenue – Wayne to Easton
Long Pond Drive
Myrtle Avenue – Maple to Saw Mill
Pershing Avenue – Watson to Washington
Prospect Avenue – Maple to Saw Mill
Saw Mill Lane
Sill Avenue
Washington Avenue
Woodland Avenue – Maple to Saw Mill
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-3 Streets
Beaver Road
Cedar Brook Drive
Dogwood Lane
Firewood Drive
Forrester Road
Greenwoods Drive
Hickory Drive
Horsham Road – Walnut to Maple
Logger Mill Road
Lumberjack Circle
Myrtle Avenue – Walnut to Maple
Prospect Avenue – Walnut to Maple
Sawbuck Circle
Whetstone Road
Woodland Avenue – Walnut to Maple
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-4 Streets
Adee Avenue
Dora Avenue
Dresher Road – Horsham to New Rd.
Fair Oaks Avenue
Hill Avenue
Horsham Road – Blair Mill to Easton
Johnson Road
Morris Road
New Road
Pine Avenue
Roberts Avenue
Ruth Avenue
Summit Avenue
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-5 Streets
Applewood Court
Brookwood Court
Brown Briar Court
MacIntosh Court
Palamino Court
Samantha Lane
Tartan Court
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-6 Streets
Ash Stoker Lane
Bark Hollow Lane
Brookside Court
Coach Road
Colonial Drive
Dogwood Lane
Ember Lane
Lamplighter Road
Lantern Lane
Norristown Road – Witmer to Chestnut Street
Sarah’s Lane
Virginia Lane
Whetstone Road
Witmer Road – Norristown to Country
Woodbine Court
Woodview Court
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-7 Streets
Chestnut Street
Gallen Road
Hallowell Avenue
Horsham Road – Norristown to Precision
Jarrett Road
Norristown Road – Horsham to Witmer
Precision Road – Horsham to Dead End
Victoria Lane
Winchester Drive
Sewer Specialty Services Company, Inc., has begun “grouting only” work in sections designated B-1, B-2, B-3, B-4, B-5, B-6, B-7 & B-8. This work will be ongoing and is anticipated to be completed by the end of May, 2013.
B-8 Streets
Blacksmith Circle
Brownstone Lane
Carriage Drive
Cobblestone Drive
Country Road
Fawn Lane
Goldlenrod Lane
Heather Lane
Horseshoe Circle
Mann Road
Meadow Circle
Old Witmer Road
Pebble Drive
Pheasant Run
School Road
Tall Pine lane
Wade Avenue
In extremely rare instances, you may notice a slight sewage odor, or “gurgling” in your drains as the sewer lines are prepared for testing. Should this occur, you should flush all toilets and run water in all sinks and bathtubs to ensure that water is in all plumbing traps. We also recommend that you make sure all toilet lids are closed and if you have basement windows in your home, you may wish to open them slightly.
Information regarding successive quadrants, interceptor sewers, or major roadway areas will be provided as work nears completion in the preceding quadrant.
If you have any questions/comments, please contact the Horsham Water & Sewer Authority at: 215-672-8011
Horsham Township Municipal Building
1025 Horsham Road
Horsham, PA 19044
Phone: (215) 643-3131
Fax: (215) 643-0448
horsham@horsham.org
Hours: Mon-Fri, 8:30 AM-4:30 PM
Horsham Township Police Department
1025 Horsham Road
Horsham, PA 19044
Emergency: 911
Non-Emergency Response: (215) 643-3600
Business: (215) 643-8284
Fax: (215) 643-0390
police@horsham.org
Hours: 24 Hours